Question: Which of the following is NOT true about Solution Backlog?
A) It is the holding area for upcoming Capabilities.
B) It is the holding area for upcoming Enablers.
C) It is intended for a single Agile Release Train only.
D) It is intended for multiple Agile Release Train.

Answer: C

Explanation: The Solution Backlog can span multiple Agile Release Trains.

--

--