SAFe Agile: Which of the following is NOT true about Program Backlog?

Dhiraj K
Sep 20, 2022

--

SAFe Agilist Certification

SAFe 5.1 Certification Exam Practice Test: Questions and Answers with explanation for SAFe Agilist Certification Exam and SAFe Scrum Master Certification Exam

Question: Which of the following is NOT true about Program Backlog?
A) It is the holding area for upcoming Features.
B) It contains the necessary enabler features.
C) It is intended for a single Agile Release Train.
D) It is intended for multiple Agile Release Train.

Answer: D

Explanation: The Program Backlog is intended for a single Agile Release Train (ART).

--

--