SAFe Agile: Which of the following is FALSE about uncommitted objectives in Program Increment Planning?

Dhiraj K
Sep 24, 2022

--

Safe Agilist Certification

SAFe 5.1 Agile Certification Exam Practice Test: Questions and Answers with explanation for SAFe Agilist Certification Exam and SAFe Scrum Master Certification Exam

Question: Which of the following is FALSE about uncommitted objectives in Program Increment Planning?
A) Uncommitted objectives help improve the predictability of delivering business value.
B) Uncommitted objectives are used to identify work that can be variable within the scope of a PI.
C) Teams can apply uncommitted objectives whenever there is low confidence in meeting the objective.
D) Teams can apply uncommitted objectives whenever there is high confidence in meeting the objective.
Answer: D

Explanation: Teams can apply uncommitted objectives whenever there is low confidence in meeting the objective.

--

--

Dhiraj K

SAFe and PSM Certified and Practicing Scrum Master and Agile Coach