SAFe Agile: Which of the following is FALSE about Program Increment?

Dhiraj K
Sep 22, 2022

--

SAFe Agilist Certification

SAFe 5.1 Agile Certification Exam Practice Test: Questions and Answers with explanation for SAFe Agilist Certification Exam and SAFe Scrum Master Certification Exam

Question: Which of the following is FALSE about Program Increment?
A) Program Increment is time-boxed.
B) Program Increment is typically Five iterations long.
C) Generally Program Increment has an Innovation and Planning Iteration.
D) Generally First Iteration in a PI is called Innovation and Planning.
Answer: D

Explanation: Generally Fifth Iteration in a PI is called Innovation and Planning.

--

--

Dhiraj K

SAFe and PSM Certified and Practicing Scrum Master and Agile Coach