SAFe Agile: Which of the following is an input to Program Increment Planning?

Dhiraj K
Sep 23, 2022

--

SAFe Agilist Certification

SAFe 5.1 Agile Certification Exam Practice Test: Questions and Answers with explanation for SAFe Agilist Certification Exam and SAFe Scrum Master Certification Exam

Question: Which of the following is an input to Program Increment Planning?
A) Committed PI objectives.
B) Program Board.
C) Roadmap and Vision.
D) Team Backlog.
Answer: C

Explanation: Roadmap and Vision is input to Program Increment Planning. Committed PI objectives and Program Board, are output to Program Increment Planning. Program Backlog is used as input, not the team backlog.

--

--